  • Project Start: August 2020
  • Projected Completion: December 2020
  • Construction Cost: 11.2M

Markets Back to Top

Industrial

Location Back to Top

Ohio

Partners Back to Top

Weston, Inc.
Developer
Independence Construction
Construction Manager/General Contractor

Summary Back to Top

Complete build out for new Amazon delivery stations including modification of 168,000 square foot warehouse, construction of interior 15,000 square foot office facility, installation of eight (8) new loading docks and four (4) van loading terminals, construction of 34,000 square foot van loading canopy, paving of approximately 16 acres for van storage parking, and paving of 2 acres of associate/customer parking.